Long Island Electric Power Grid Construction
Long Island Electric Power Grid Construction
This was a turn-key project that built a new underground electric power grid to provide a stable power supply to the Long Island adjacent to Manhattan, New York. A turn-key order in the US market is very unusual. Taihan was highly recognized for its excellent products and technologies by the client, and carried out the entire process from product supply to electrical work, civil engineering work, and completion test in about one year.
Supplied products and solutions
- 138kV EHV XLPE cables
- EHV XLPE cable accessories
- Engineering and construction
- Commissioning test
Compete with Technologies
This project has a significant meaning in that it was carried out as a technology bidding proposing technology and construction methods, etc., rather than a simple bidding proposing a price according to the specifications of the client. In addition, it was a great achievement that Taihan won the order confidently by winning the competition not only against local companies in the US but also against major global cable companies in Korea, Europe, and Japan, etc. This shows that Taihan's customized solutions, engineering capabilities, and project execution capabilities, etc. are being highly recognized, and also means that it established itself as a major supplier in the US market.